La Esperanza La Isla

Project Start Date:Friday, February 4, 2011
Completion Date:12/4/2011
Target Completion-
People:173
Number of Homes:33

Project Details

  • Survive by subsistence farming
  • All labor was provided by villagers with no monetary compensation
  • Spring output quantity 72,000 liters/day(excess of La Isla spring)
  • Required for 1.5x population 24,000 liters/day
  • Conduction pipeline length of 3588 feet was installed manually 1 meter deep
  • Storage tank of 54 cubic feet was constructed
  • Distribution pipeline network length of 26,250 feet(5 miles) was installed manually 1 meter deep bringing water to each residence plus the school & church
  • Safe drinking water outlets were installed in 33 backyards
  • 25 latrines were constructed