La Esperanza La Isla
Project Start Date: | Friday, February 4, 2011 |
Completion Date: | 12/4/2011 |
Target Completion | - |
People: | 173 |
Number of Homes: | 33 |
Project Details
- Survive by subsistence farming
- All labor was provided by villagers with no monetary
compensation
- Spring output quantity 72,000 liters/day(excess of La Isla
spring)
- Required for 1.5x population 24,000 liters/day
- Conduction pipeline length of 3588 feet was installed manually
1 meter deep
- Storage tank of 54 cubic feet was constructed
- Distribution pipeline network length of 26,250 feet(5 miles)
was installed manually 1 meter deep bringing water to each
residence plus the school & church
- Safe drinking water outlets were installed in 33 backyards
- 25 latrines were constructed