Palan Bilampi

Project Start Date:Friday, February 1, 2013
Completion Date:8/15/2013
Target Completion Date:8/15/2013
People:169
Number of Homes:29

Project Details

  • Population 169 People 38% in agriculture & ranching. 38% are day labor on farms, 24% are subsistence farmers
  • All labor was provided by villagers with no monetary compensation
  • Spring output = 98000 liters per day
  • Water quantity required for 1.5X current population = 28,500 liters per day
  • Conduction line length = 4530 feet
  • Storage tank size = 90 Cubic feet
  • Distribution network length = 11,000 feet
  • Safe drinking water outlets were installed @ 29 houses & @ school
  • New latrines were constructed at 28 residences needing them