Varsovia

Project Start Date:Wednesday, April 1, 2009
Completion Date:12/1/2009
Target Completion-
People:350
Number of Homes:70

Project Details

  • Two (2) springs were encapsulated to provide sufficient water
  • 8100 linear feet (1.5 miles) of pipe were installed manually 1 meter deep to bring water from spring to storage tank
  • A reinforced concrete storage tank of 108 cubic feet was constructed
  • 40,000 linear feet (almost 8 miles) of distribution piping were installed to bring water to each residence plus the school & church
  • Safe drinking water outlets were installed in 70 backyards.
  • Latrines were constructed on each residential property plus the school & church.