Walana el Achiote

Project Start Date:Tuesday, January 10, 2012
Completion Date:12/1/2012
Target Completion-
People:141
Number of Homes:29

Project Details

  • Population --23% in agriculture, 50% ranching, 23% day labor on farms
  • All labor was provided by villagers with no monetary compensation
  • Stream output = 141,000 liters per day,  
  •            water quantity required for 1.5X current population = 19,000 liters per day
  • Conduction line length=26,500 feet/5 miles
  • Storage tank size=63 cubic feet
  • Distribution network length=41,500 feet/8 miles
  • Safe drinking water outlets have been installed at 29 houses + 2 schools & church
  • New latrines have been built at the 21 residences needing them